Ware Street

Project Overview
Client Name
Heinrichs Developments
Timeline
July 2023 – October 2023
Scope of Work
Installation of a new 600mm storm sewer, including excavation, shoring, trenching, and backfill, in a high-traffic urban area.
The Challenge
The project site was a busy road with extremely deep excavations (over 5 meters) in unstable sandy pit-run material. Safety was a major concern due to the risk of trench collapse, vehicular traffic, and worker protection. Traditional straight-cut trenching was not feasible due to material instability, requiring extensive shoring and lane closures.
Our Approach + Results
We adapted by using a combination of partial slope cuts and caged trench bottoms, allowing safe installation of the storm line. To minimize risks to traffic and workers, all excavation and installation were completed during night shifts. This approach ensured worker safety, maintained traffic flow as much as possible, and allowed the project to be completed on schedule while meeting all engineering and safety requirements.