Project Overview

Client Name

Heinrichs Developments

Timeline

Approximately 18 Months (Ongoing – 6 Months Completed to Date, with intermittent work anticipated through Summer 2027

Scope of Work

Silverstone Excavating is executing bulk excavation exceeding 20 feet in depth and site preparation for the development's underground parkade on a confined site. To safely manage the property boundaries, they will install an engineered temporary shoring system featuring shotcrete-faced walls and soil anchors in controlled stages, followed by the installation of comprehensive underground utility systems, including sanitary, storm, and water services.

Scout is a multi-family residential development located at 2790 Gladwin Road and 32845 Ventura Avenue in Abbotsford, BC. The project involves extensive bulk excavation, temporary shoring, and underground civil infrastructure construction, including a deep excavation exceeding 20 feet to accommodate the development's underground parking structure.

Silverstone Excavating is responsible for completing the bulk excavation and onsite civil infrastructure, with additional offsite municipal servicing and roadway improvements scheduled for later phases of construction.

Silverstone Excavating's scope includes extensive bulk excavation, material removal, and site preparation for the development's underground parkade. The excavation exceeds 20 feet in depth and extends to the property's boundaries, requiring closely coordinated excavation and temporary shoring operations to accommodate the proposed building footprint within the confined site.

The project incorporates an engineered temporary shoring system consisting of shotcrete-faced excavation walls, soil anchors, and associated ground support measures. Excavation progresses in controlled stages to accommodate the installation of the shoring system and maintain stability as the excavation reaches its final design elevations.

Following bulk excavation, Silverstone's scope includes installation of onsite underground utilities, including sanitary sewer, storm drainage, water servicing, and associated stormwater management infrastructure.

Future phases will include offsite municipal infrastructure upgrades and roadway improvements along Gladwin Road and Ventura Avenue, including underground utility connections, concrete curbs and sidewalks, and associated surface restoration.

The Challenge

The primary challenge is completing a deep bulk excavation exceeding 20 feet in depth within an extremely confined urban site, with excavation extending directly to the property boundaries on all sides. The limited working space creates significant challenges for equipment positioning, truck access, material handling, and the installation of temporary excavation support.

The site's coarse pit-run material further complicates excavation and ground stabilization. Maintaining stable excavation faces while exposing and removing the granular material requires carefully controlled excavation methods and close coordination with the shoring operations.

With virtually no room for conventional sloped excavation, extensive engineered shotcrete shoring is required around the excavation perimeter. Excavation must progress in carefully controlled stages, allowing the shoring system to be installed as the pit advances deeper. This requires precise sequencing and coordination to maintain safe working conditions while protecting adjacent properties and infrastructure.

Our Approach + Results

Silverstone Excavating is executing the bulk excavation through a carefully sequenced approach coordinated with the engineered temporary shoring system. Excavation progresses in controlled stages, allowing soil anchoring and shotcrete applications to be completed as the excavation advances toward the required parkade elevations.

The team is managing the challenging ground conditions and restricted working area through coordinated equipment operations, material removal, and close collaboration with the geotechnical and shoring teams. This approach allows excavation to progress within the property's tight boundaries while maintaining the necessary ground support.

Following completion of the bulk excavation, Silverstone will transition into the onsite civil servicing works, including underground utilities and stormwater management infrastructure. Subsequent phases will involve offsite municipal servicing and roadway improvements along Gladwin Road and Ventura Avenue.

With approximately six months of work completed to date, the project is anticipated to continue through summer 2027 as construction progresses through its remaining phases.

The project demonstrates Silverstone's capabilities in complex deep excavation, constrained urban construction, and coordination of engineered shoring systems. The combination of challenging ground conditions, significant excavation depths, and minimal working space highlights the technical planning and construction expertise required to deliver large-scale residential developments in densely developed areas.