Port Coquitlam Transit Centre

Project Overview
Client Name
Black & McDonald Ltd. / Translink
Timeline
24 - 36 Months (Ongoing – 12 Months Completed to Date)
Scope of Work
Silverstone Excavating's scope includes extensive excavation, trenching, and construction of concrete-encased electrical duct banks throughout the transit centre.
The Port Coquitlam Transit Centre Electric Bus Charging Infrastructure project is a major multi-year infrastructure upgrade supporting TransLink's transition toward a battery-electric bus fleet. Located at TransLink's active transit facility in Port Coquitlam, BC, the project involves extensive underground electrical infrastructure, concrete-encased duct banks, structural equipment foundations, and roadway improvements to accommodate new electric bus charging systems.
Working alongside Black & McDonald, Silverstone Excavating is responsible for the civil and structural concrete components of the project, delivering the infrastructure required to support the facility's electrification while maintaining uninterrupted transit operations.
Silverstone Excavating's scope includes extensive excavation, trenching, and construction of concrete-encased electrical duct banks throughout the transit centre. Major components include approximately 800 linear metres of private secondary electrical duct bank and 200 linear metres of primary BC Hydro service duct bank, in addition to an extensive network of underground conduit systems connecting the electric bus charging infrastructure.
The duct bank installations vary considerably in size and configuration, ranging from smaller conduit runs to large, multi-conduit concrete-encased structures approaching 15 feet in width. Silverstone is responsible for excavation, trench preparation, coordination with the electrical contractor for conduit placement, concrete encasement, backfilling, and compaction.
The project also includes substantial structural concrete construction, comprising 48 reinforced concrete charging island foundations accommodating 72 charging dispenser positions. Each foundation incorporates a concrete curb and gutter surround with protective bollards. Additional structural concrete work includes six transformer pads, five kiosk pads, and four charging cabinet foundations. Silverstone has completed the cast-in-place concrete installations and coordinated the design and fabrication of select precast concrete components.
Further civil works include demolition of existing pavement, site grading, granular base preparation, asphalt paving, and reconstruction of affected transit yard surfaces.
The Challenge
The primary challenge is executing extensive underground electrical infrastructure and structural concrete construction within a fully operational transit facility. Throughout construction, TransLink's bus yard has remained active, requiring careful coordination around continuous bus movements, parking operations, and daily transit schedules.
The scale of the underground electrical infrastructure presents significant logistical challenges. Large duct bank installations require substantial excavation through existing paved areas, often within active bus circulation routes. Maintaining safe working areas while preserving operational access for buses and facility personnel requires detailed planning and continuous coordination.
An additional complexity is the integration of civil and electrical construction activities. Each duct bank installation requires carefully sequenced excavation, conduit placement, concrete encasement, and backfilling, with precise alignment and elevation requirements. These activities must be coordinated alongside structural foundation construction and yard restoration while minimizing interference with transit operations.
Our Approach + Results
Silverstone Excavating has implemented a carefully phased construction strategy designed to accommodate ongoing transit operations while progressing through the extensive underground infrastructure installations. Work areas are coordinated with TransLink and Black & McDonald to maintain essential bus circulation routes, manage construction access, and minimize disruption to daily yard activities.
Close collaboration between the civil and electrical contractors has been critical to the project's progress. Silverstone completes excavation and trench preparation, allowing the electrical contractor to install the extensive conduit systems before Silverstone returns to complete concrete encasement, backfilling, and restoration. This coordinated approach supports efficient construction of the large duct bank network while maintaining the accuracy required for the electrical infrastructure.
In addition to the underground installations, Silverstone has undertaken substantial structural concrete construction, including charging island foundations, concrete curb and gutter surrounds, protective bollards, transformer pads, kiosk foundations, and charging cabinet foundations. Select precast components were also designed and fabricated to accommodate specific project requirements.
After approximately 12 months of construction, the project is reaching its first major paving milestone, allowing completed work areas to be restored while subsequent phases continue. Throughout this period, TransLink's bus yard has remained operational.
With an anticipated overall duration of two to three years, the project demonstrates Silverstone's ability to deliver large-scale electrical civil infrastructure and structural concrete construction within a continuously operating transit facility. The work highlights Silverstone's technical capabilities, construction coordination, and experience delivering critical infrastructure improvements while maintaining essential public transit operations.