Nottman 

Nottman

Project Overview

Client Name

Westcorp Ventures Ltd.

Timeline

12 Months

Scope of Work

Site clearing, stripping, bulk excavation, earthworks, and extensive grading and preparation of multiple townhouse building pads.

Silverstone Excavating's scope involved placing and compacting structural fill to establish the required building elevations and provide suitable foundations for the proposed residential structures.

The project also included installation of onsite and offsite water, sanitary sewer, and storm drainage infrastructure, including municipal watermain upgrades, service connections, manholes, catch basins, and stormwater management systems.

Additional work included construction of internal roadways and private lanes, installation and coordination of underground electrical and telecommunications services, and completion of offsite road improvements along Nottman Street and Cherry Avenue. Roadworks included concrete curbs, gutters, sidewalks, asphalt paving, and associated surface restoration.

The Challenge

While the development did not present significant unusual technical challenges, its size and comprehensive scope required careful coordination of multiple construction activities. Extensive earthworks and building pad preparation had to be integrated with underground servicing and internal roadway construction to establish the required elevations throughout the development.

Offsite municipal utility installations and road improvements along Nottman Street and Cherry Avenue also required recurring traffic restrictions and temporary road closures. Maintaining access for surrounding residents while completing underground utility connections and roadway reconstruction was an important consideration throughout construction.

Our Approach + Results

Silverstone Excavating completed the project through a coordinated, phased construction approach, beginning with site preparation, bulk earthworks, and grading to establish the development's building pads and roadway elevations. Structural fill was placed and compacted to meet the required geotechnical specifications, creating suitable building platforms for the townhouse construction.

Underground water, sanitary, storm, electrical, and telecommunications infrastructure was installed in coordination with the site's grading and road construction activities. Offsite improvements were carefully sequenced with traffic management measures to accommodate municipal utility upgrades while maintaining access to neighbouring properties.

The project was successfully completed over a 12-month construction period, delivering the site preparation, underground infrastructure, and roadway improvements necessary to support the townhouse development. The completed work demonstrates Silverstone's ability to manage large-scale residential site development, from initial earthworks and building pad preparation through to municipal servicing and road construction.