Skyview Residential Site 

Skyview Residential Site

Project Overview

Client Name

Bianco Developments

Timeline

January 2024 – January 2025

Scope of Work

Complete site servicing and roadworks, including installation of watermain, storm and storm detention systems, sanitary services, hydro, communications, street lighting, curbs, sidewalks, and paving.

The Challenge

The project faced several challenges, including steep site slopes, high groundwater levels, and the requirement for separate storm and sanitary services for two apartment buildings, all while maintaining efficient construction sequencing.

Our Approach + Results

Working closely with the project engineers, we implemented a dual-pipe manhole system that allowed the apartment buildings to maintain separate services while sharing the same manholes. This solution simplified installation, reduced site disruption, and ensured compliance with design requirements. The project was completed on schedule, providing a fully serviced site ready for occupancy.

  • Gallery image
  • Gallery image
  • Gallery image
  • Gallery image
  • Gallery image