Numbers Bulk and Detail Excavation

Project Overview
Client Name
Whitetail Homes
Timeline
March 2025 – September
Scope of Work
Excavation for building pads and footings, shotcreting, mechanical infrastructure installation under the parkade slab, and slab preparation. The work required careful planning and sequencing due to challenging ground conditions and the need for continuous progress without returning to previously completed areas.
The Challenge
The site consisted of very soft blue clay, requiring all equipment to remain on swamp mats to avoid sinkage. Excavation had to be carefully planned and executed to prevent rework, and maintaining stability while moving heavy equipment and materials was critical.
Our Approach + Results
We used a coordinated approach with multiple excavators working together, bailing to each other, and employing a telebelt for precise gravel placement. Swamp mats were strategically deployed to support equipment, and work progressed systematically from one area to the next. This approach allowed us to complete all excavation, mechanical preparation, and slab work efficiently, safely, and on schedule despite the difficult ground conditions.