King Crescent Townhouse

Project Overview
Client Name
Central Valley Engineering
Timeline
6 Months
Scope of Work
Silverstone Excavating delivered complete site prep for the townhouse development, encompassing excavation, grading, underground civil utilities, municipal watermain upgrades, and electrical/telecom infrastructure. Scope highlights also included internal roadway construction with off-site asphalt restoration, alongside a 57-metre engineered concrete lock-block retaining wall designed for slope stability.
The King Crescent Townhouse Development project involved comprehensive site servicing, earthworks, and road construction for a new 20-unit residential townhouse development located at 1641 and 1643 King Crescent in Abbotsford, BC. Silverstone Excavating was responsible for preparing the site for development, installing underground municipal infrastructure, constructing internal roadways, and completing a substantial retaining wall system to accommodate the site's elevation changes and proposed building grades.
Silverstone Excavating's scope included full-site excavation, earthworks, grading, and installation of underground water, sanitary sewer, and storm drainage infrastructure. The project involved off-site municipal watermain upgrades along King Crescent, new water, sanitary, and storm service connections, stormwater infiltration systems, and associated underground servicing for the townhouse development.
Additional work included electrical and telecommunications infrastructure upgrades, including BC Hydro and TEL service installations, construction of internal roadways, asphalt paving, and associated off-site road restoration. A significant component of the project was the construction of an approximately 57-metre-long engineered concrete lock-block retaining wall along the northern property boundary, complete with structural backfill and drainage provisions to accommodate the site's varying elevations.
The Challenge
One of the primary challenges was completing extensive underground utility upgrades and roadworks within an established residential neighborhood. The installation of a new municipal watermain, electrical and telecommunications infrastructure, and associated road improvements required frequent closures along King Crescent. Maintaining neighborhood access, managing traffic, and coordinating multiple utility installations within an active residential area presented significant logistical challenges.
The site's varying elevations created an additional challenge, requiring a substantial engineered retaining wall to establish the necessary grades for the townhouse buildings and internal roadways. Integrating the retaining wall construction with the site's earthworks and underground infrastructure required careful planning and sequencing to achieve the proposed development elevations.
Our Approach + Results
Silverstone Excavating coordinated the underground utility installations and road construction through carefully sequenced work phases, managing traffic control and temporary road closures to accommodate construction activities while minimizing disruption to surrounding residents. The team completed the municipal watermain replacement, electrical and telecommunications upgrades, and underground servicing alongside the development's internal roadworks and off-site improvements.
To address the site's elevation challenges, Silverstone constructed an engineered concrete lock-block retaining wall along the northern property boundary, incorporating a compacted structural foundation, drainage materials, and engineered backfill. The retaining wall established the necessary grade separation to accommodate the proposed building elevations and maximize the usable development area.
The project was successfully completed over a six-month construction period, delivering the underground utilities, municipal infrastructure upgrades, retaining wall, and roadworks necessary to support the new residential development.