134 Street and 27 Avenue Sanitary Sewer Upgrade 

134 Street and 27 Avenue Sanitary Sewer Upgrade

Project Overview

Client Name

Paragon Homes Ltd.

Timeline

1 Month

Scope of Work

Deep trench excavation, installation of approximately 50 linear meters of 200 mm PVC sanitary sewer, associated manhole and connection works, trench backfilling, compaction, and restoration of disturbed surfaces.

The project also required excavation and material removal through exceptionally hard ground conditions, coordination around existing underground municipal infrastructure, and management of construction access within the surrounding neighborhood.

The Challenge

The project presented two primary challenges: difficult deep excavation conditions and maintaining public safety near an active school.

The sanitary sewer installation required excavation to significant depths through exceptionally hard ground, making excavation and material removal considerably more demanding than typical underground utility construction. These conditions required careful management of equipment operations, trench stability, and the installation sequence.

Equally important was the project's proximity to a school. Construction activities had to account for increased pedestrian activity, particularly during morning drop-off and afternoon pickup periods. Heavy equipment operations, construction vehicle movements, and open excavations required heightened attention to safety and coordination.

Maintaining a safe environment for students, parents, school staff, and the surrounding community was a central priority throughout the project.

Our Approach + Results

Silverstone Excavating approached the project with a focus on efficient construction, controlled excavation, and public safety.

The team coordinated excavation and material removal through the difficult ground conditions while maintaining safe trenching practices and progressing with installation of the new sanitary infrastructure.

Special consideration was given to construction vehicle movements, pedestrian access, and separation of active work areas from school-related traffic. Construction activities were planned with awareness of school schedules to reduce potential conflicts during peak pedestrian periods.

Despite the challenging excavation conditions and sensitive location, Silverstone successfully completed the sanitary sewer upgrade within one month.

The project demonstrates Silverstone's ability to deliver demanding underground infrastructure installations efficiently while maintaining a strong focus on public safety, particularly in active residential neighborhoods and areas surrounding schools.